Year
|
Location |
Client |
Size |
Voltage |
Remarks |
2018 |
Man Kok Tsui to Hei Ling Chau
(Near Man Kok Tsui)
|
CLP |
95Cu |
11kV |
Repair Work
Cable Detection, De-burial & Reburial to 2.0m, Cable Landing + Concrete Slabs Protection
& Articulated Pipes Protection
|
2014 |
Man Kok Tsui to Hei Ling Chau
(Near Hei Ling Chau)
|
CLP |
95Cu |
11kV |
Repair Work
Cable Detection, De-burial & Reburial to 2.0m
+ Concrete Slabs Protection
& Articulated Pipes Protection
|
2013 |
Hong Kong International Airport to Sha Chau
(Near Hong Kong International Airport)
|
CLP |
95Cu |
11kV |
Repair Work
Cable Detection, De-burial & Reburial to 2.0m
|
2013 |
Man Kok Tsui to Hei Ling Chau
(Near Man Kok Tsui)
|
CLP |
95Cu |
11kV |
Repair Work
Cable Detection, De-burial & Reburial to 2.0m
+ Concrete Slabs Protection
|
2007 |
Kau Lau Wan to Tap Mun |
CLP |
95Cu |
11kV |
Repair Work
Cable Retrieval & Surface Lay + Articualted Pipes Protection
|
2006 |
Sham Shui Kok, Lantau Island to Siu Mo To Island
|
CLP |
95Cu |
11kV
|
Repair Work Cable Detection, De-Burial & Reburial to 2.5m + Concrete Slabs Protection
|
2005 |
Discovery Bay to Peng Chau No. 1 And No. 2
|
CLP |
185Cu |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 3.0m + Concrete Slabs Protection |
2005 |
Discovery Bay Area 4C Bay to Peng Chau LOT 660 |
CLP |
95Cu |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 3.0m + Concrete Slabs Protection |
2005 |
Chok Tsai Wan Lin, to Hei Ling Chau No. 1 |
CLP |
70Cu |
11kV |
Concrete Slabs & Articulated Pipes Protection |
2004 |
Chok Tsai Wan Lin, Lantau to Hei Ling Chau No. 1 (At Chok Tsai Wan) |
CLP |
70Cu |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 1.5m + Concrete Slabs Protection |
2004 |
Tsing Yi to Ma Wan |
CLP |
70mm |
11kV |
Cable Recovery |
2004 |
Peng Chau to Kau Yi Chau |
CLP |
95mm |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 1.5m + Articulated Pipes Installation (Coral Rocks at tidal section) |
2004 |
Tai O River |
CLP |
70mm |
11kV |
Cable Replacement Replace 3 nos. of 11kV & Optical Fiber + Articulated Pipes Installation |
2004 |
On Lok Road, Hong Kong to Shekou, P.R.C. No. 2 (Near Shenzhen Western Corridor) |
CLP |
380Cu |
132kV |
Concrete Slabs Protection, Cable Detection & De-Burial to 5.4m |
2003 |
On Lok Road, Hong Kong to Shekou, P.R.C. No. 1 (At Shekou, P.R.C.) |
CLP |
70mm |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 1.5m & Reburial to 3.0m |
2003 |
Chok Tsai Wan Line to Hei Ling Chau No. 1 (At Hei Ling Chau) |
CLP |
70mm |
11kV |
Repair Work Cable Detection, De-Burial & Reburial to 1.5m & Reburial to 3.0m |
2003 |
Tai Mong Tsai to Kiu Tsui |
CLP |
125mm |
11kV |
Installed 1.4km Concrete Slabs to protect the 11kV Submarine Cable Circuit |
2001 |
Sai Kung to Po Lam |
CLP |
110mm |
132kV |
Installed 1.4km Concrete Slabs to protect the 132kV Submarine Cable Circuit |
2000 |
Sha Chau |
CLP |
95mm |
11kV |
Repair Work Locate Cable, De-Burial & Reburial to 1.5m & Reburial to 3.0m |
1999 |
Peng Chau to Discovery Bay |
CLP |
70mm |
11kV |
Repair Work Locate Cable, De-Burial & Reburial Work |
1994 |
Discovery Bay to Lok On Pai No.2 |
CLP |
230mm |
33kV |
Repair Work Locate Cable, De-Burial & Reburial Work |
1994 |
Tuen Mun to Discovery Bay |
CLP |
120mm |
11kV |
Cable Diversion |
1994 |
Siu Lam |
CLP |
- |
33kV |
Cable Diversion |
1993 |
Tuen Mun to Discovery Bay |
CLP |
120mm |
33kV |
Repair Work Locate Cable, De-Burial & Reburial Work |